Street widening and stormwater on a live residential road
The traffic conditions set the price before any rate did.
- Region
- SEQ, regional council
- Client
- Regional civil contractor
- Disciplines
- Road widening and pavement, kerb, trunk stormwater, culvert extension, traffic management
- Value
- $1M to $5M
What we delivered
- Method agreed first: single lane shuttle, short blocks completed one at a time
- Estimate on that method across circa 720 m of corridor and circa 880 m of stormwater
- Programme by block, with staged priming so no lane reopened unsealed
- Methodology, draft TMP and the non-price returnables